HS2 in Northants logoHS2 in Northants

Get project news

Do you want to receive an email when news items are posted?

News on HS2 in Northants

Back to news

HS2 Notification: Update of works Greatworth to Thorpe Mandeville, May - December 2021

As part of our continuing works ahead of the construction of the railway we are undertaking some further work in your area. Our activity in the Greatworth to Thorpe Mandeville area is well underway with the main works compound known as the ‘Greatworth Green Tunnel Compound’ being set up and some early construction works starting. Over the summer our activity will extend from the compound and you can expect to see the following works in the local area:

• Ground Investigations (GI);

• Utility works including trial holes;

• Land surveys to measure land levels;

• Completion of the ‘Greatworth Green Tunnel’ Compound;

• Installation of a concrete batching plant;

• Localised clearance of vegetation and fencing along the line of the route;

• Construction of access and haul roads to move people, material, and earthworks along the line of the new railway, rather than on local roads;

• Excavation, movement, and storage of earthworks; and

• Some short duration traffic management and temporary footpath diversions to carry out some of the above activities.

For further information, please see our notification https://www.hs2.org.uk/work-items/hs2-update-greatworth-to-thorpe-mandeville/

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk

Posted on 21st May 2021

by HS2 in Northants