HS2 Work Notification: Notice of work at the A43 and road closures - early June

We are setting up our compound and temporarily diverting the A43 to carry out our construction activities. This will include:

1. Ground Investigation (GI) works

2. Utility works and surveys including trial holes

3. Build an access into the compound

4. Setting up a works compound

5. Localised clearance of vegetation and fencing

6. Excavation, movement and storage of earthworks

To carry out our work on the northbound carriageway, we will need to close the A43 between the Northampton Road Brackley roundabout (BP roundabout) and the Syresham Junction, Welsh Road, overnight from 20:00 to 6.00am.

To find out further information please see our notification https://www.hs2.org.uk/work-items/notice-of-work-at-the-a43-site-investigations-and-compound-set-up/

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk

Posted on 21st May 2021

by HS2 in Northants